“We’ll do it in a week” and “it takes six months” can be about the same site. We break down real timelines by site type, the work stages and the main causes of delays.

June 7, 2026
9 min read
42 views
MOLOTILO

MOLOTILO DIGITAL

How long a site takes to build: real timelines from a landing page to a store and what derails them

Why the timelines quoted are so different

One contractor promises a site in a week, another quotes three months for the same request. Both can be honest: the first means a template with a logo swap, the second a full build with analytics and content. To compare offers, you need to understand which stages make up the timeline and what can actually be compressed.

Real timelines by site type

  • A template landing page — 3–7 days.
  • A custom landing page — 2–4 weeks (prototype, text, design, markup).
  • A services site / brochure — 3–6 weeks.
  • A corporate site — 1.5–3 months.
  • An online store — 2–4 months (with 1C and delivery integrations — closer to the upper bound).
  • A portal, service, personal accounts — from 3–6 months.

These are timelines at a normal pace of approvals. How they relate to the budget — see the breakdown of website costs in 2026.

Stages and their duration (using a corporate site as an example)

  1. Analysis and the technical spec — 1–2 weeks. Who your audience is, the structure, semantics, prototypes of key pages.
  2. Design — 2–4 weeks: concept, approval, the remaining pages.
  3. Markup and development — 3–6 weeks: frontend, admin panel, integrations.
  4. Filling with content — 1–3 weeks, if the content is ready (spoiler: usually it is not — more on that below).
  5. Testing and launch — 1 week: checking on devices, forms, speed, backups, analytics.

What actually derails timelines

In our experience, the main cause of delays is not the developers but downtime on the client’s side:

  • Content. Texts “we’ll send them any day now” delay launch by months. The fix: write in parallel with the design or order the texts from the contractor.
  • Approvals. The design sits “for review” with the director for a week — plus a week to the timeline. Appoint one person responsible with decision-making authority.
  • Edits in circles — “show it in blue too”, then “put it back”. Cured by a prototype and locking edits into iterations.
  • Scope creep on the fly: “since we’re at it, let’s add a personal account” — that is not an edit, it is a new project inside the project.
  • Access and technical dependencies: the domain is with a vanished freelancer, the 1C specialist is on vacation, the acquiring paperwork takes three weeks.

How to speed up launch without losing quality

  1. Launch in stages: the core of the site first, the blog and extra sections as a second release. The site starts working and bringing leads sooner.
  2. Prepare the content in advance — before design starts.
  3. Assign someone responsible with the authority to make decisions in 1–2 days.
  4. Gather the access (domain, hosting, 1C, CRM) before work begins.

Careful: “a site in 3 days”

A promise to build a full site in a few days means one of two things: a template not adapted to your business, or work without analysis and testing. For testing a hypothesis — fine. For a company’s main site — you get a product you will have to redo. The stingy pay twice, the hasty three times.

Conclusion

Real timelines: a landing page — 2–4 weeks, a services site — up to a month and a half, a corporate site — 2–3 months, a store — 2–4 months. Half the success on timelines is on the client’s side: ready content, fast approvals, gathered access. We will name an exact timeline for your task with a week-by-week plan — write to us.